COFICO executes the concrete pouring for the basement of Saigon Airport Plaza complex building

In the night of 15 Mar, 2011, from 21h30 until the dawn of 16 Mar, on the site of Saigon Airport Plaza project, COFICO has urged to complete the pouring concrete for the first zone among of 9 zones of basement floor B2 of this complex building. The volume of concrete poured in the night was 1,610 m3. To execute this work, 8 concrete pumping machines have been simultaneously operated altogether with the staffs, workers rushing to accomplish the work to ensure its timeline and quality. dsc05145

Being the contractor to execute the 1st stage of the complex building, COFICO has started the construction since 10/2010 and always be appreciated its effective organization and professional performance.

In the night of 20 Mar, 2011, COFICO continues the concrete pouring of 2,200 m3 for zone 3. Though it was the weekend, all staffs and workers still work tensely in order to carry out this important job thoroughly.

dsc05148 With total area of 1.6 acres including five towers which connect to each other: an office tower, three apartment towers and a hotel tower connected with the airports through a bridge or a tunnel, SAP complex is evaluated to be one of a highlight project of COFICO this year. dsc05154 dsc05159 dsc05161 dsc05164 photo

Newer post

Older post

COFICO’S CORE VALUES
REPUTATION FOR HEALTH, SAFETY & ENVIRONMENT
CORE-VALUES_FINISHED1
MODERN TECHNOLOGY
CORE-VALUES_FINISHED1