Update projects in 2020

In the last months of the year, all works were rushing to progress. COFICO and our partners have taken advantage of the capabilities and resources to important milestones as planned and ensure that the projects are completed as committed to the investors. Some photos of the works in the last days of 2019   In the North of Vietnam: Parkcity Villa Project
  • In process of finishing to hand over the Investor
  Tay Ho Tay Villas Project
  • Completing defects and additional works
  In the Central of Vietnam: Nam Hoi An Condotel Project
  • In the process of finishing the exterior and interior
  • Waiting for acceptance of all parties as planned
  Go Mall Project – Quang Ngai
  • Preparing to hand over the shopping mall
  • Completing infrastructure items
  • Preparing for acceptance – handover – and waiting for grand opening of the project
  Hoya Lens Project – Quang Nam
  • Handed over Factory 1 for production
  • Completing Factory 2
    In the South of Vietnam: Tirol Choco Vietnam Project – Dong Nai
  • Finishing ceilings, partitions, surrounding walls, plaster walls in 2F.
  • Building office walls
  Haruka Project – Binh Dương
  • Finishing the final stage
  • Preparing for acceptance and handover of works
  Marubeni Project – Ba Ria – Vung Tau
  • Complete pouring concrete floor
  • Complete – Acceptance – Handover of warehouses, offices,…
  GS E-Tower Project – Dong Nai
  • Completed the construction of piles
  Soho Residence Project – Ho Chi Minh City
  • Complete the foundation
  • Carrying out construction methods, concreting, etc.
  Senturia Nam Sai Gon Project – Ho Chi Minh City  